Q.

Which of the following statements is true?

A. PERT is considered as a deterministic approach and CPM is a probabilistic techniques.
B. PERT is considered as a probabilistic techniques and CPM is considered as a deterministic approach.
C. PERT and CPM are both probabilistic techniques.
D. PERT and CPM are both considered as deterministic approachs.
Answer» B. PERT is considered as a probabilistic techniques and CPM is considered as a deterministic approach.