A. | PERT is considered as a deterministic approach and CPM is a probabilistic techniques. |
B. | PERT is considered as a probabilistic techniques and CPM is considered as a deterministic approach. |
C. | PERT and CPM are both probabilistic techniques. |
D. | PERT and CPM are both considered as deterministic approachs. |
Answer» B. PERT is considered as a probabilistic techniques and CPM is considered as a deterministic approach. |