Which of the following statements is true? |
| A. | PERT is considered as a deterministic approach and CPM is a probabilistic techniques. |
| B. | PERT is considered as a probabilistic techniques and CPM is considered as a deterministic approach. |
| C. | PERT and CPM are both probabilistic techniques. |
| D. | PERT and CPM are both considered as deterministic approachs. |
| Answer» B. PERT is considered as a probabilistic techniques and CPM is considered as a deterministic approach. | |