In CBR test, the value of CBR is calculated at |
| A. | 2.5 mm penetration only |
| B. | 5 mm penetration only |
| C. | both 2.5 and 5 mm penetration |
| D. | none of these |
| Answer» C. both 2.5 and 5 mm penetration | |
View all MCQs in
Highway EngineeringNo comments yet