Q.

The stress in the dam should be within the specified limits for the body of dam in the foundations. If the stress at the toe and heel are excessive, they can be brought within permissible limits by

A. Grouting
B. Providing anchor blocks
C. Providing friction blocks
D. Providing filters
E. Any of the above
Answer» D. Providing filters