A and B entered into a contract for A to construct a 20-door apartment for B. Payment shall start after the construction of ten (10). A subsequent agreement was entered into that payment will start after construction of seven (7). What is the effect of the subsequent agreement? |
A. | It is extinguished the obligation partly because of novation; |
B. | It is a modificatory novation as there was a change in the principal terms and conditions of the contract; |
C. | It is an extinctive novation as the two (2) agreements are incompatible; |
D. | It did not alter the relationship as it has no effect at all. |
Answer» B. It is a modificatory novation as there was a change in the principal terms and conditions of the contract; |