Which of the following are parameters involved in computing the total cost of a software development project? |
| A. | hardware and software costs |
| B. | effort costs |
| C. | travel and training costs |
| D. | all of the mentioned |
| Answer» D. all of the mentioned | |
| Explanation: all these are accounted for in estimating a software development cost. | |