Pick up the correct statement from the following: |
A. | the earth work of cutting in trenches or borrow pits in fairly uniform ground is measured with the help of average depths of the dead men |
B. | the earth work in trenches or borrow pits in irregular ground is measured by taking the difference in levels before and after completion of work |
C. | the earth work in trenches or borrow pits, where neither a nor b is feasible, are measured from the fillings after deduction of voids |
D. | all the above |
Answer» D. all the above |
View all MCQs in
Estimating and CostingNo comments yet