| Q. |
Which of the following is best for handling cross-functional project needs for a large, complex project |
| A. | a strong matrix organization |
| B. | a project coordinator |
| C. | a project expeditor |
| D. | direct executive involvement |
| Answer» A. a strong matrix organization | |