The open or loosely structured project organization does not rely on well-defined standards and procedures for guiding the work efforts. Therefore, this organization should be used for __________. |
A. | innovative or creative work with high-level professionals |
B. | routine work and with a new staff. |
C. | production operations and with the construction industry |
D. | . planning operations and with the functional staff. |
Answer» A. innovative or creative work with high-level professionals |