Q.

On a project, quality should generally be of

A. equal priority with cost and schedule
B. lower priority than cost and schedule
C. equal priority with cost, but higher priority than schedule
D. equal priority with schedule, but higher priority than cost
Answer» A. equal priority with cost and schedule