Q.

In case of anticipatory breach, the aggrieved party may treat the contract;

A. As discharged and bring an immediate action for damages
B. As operative and wait till the time for performance arrives
C. Exercise option either (a) or (b)
D. None of these
Answer» C. Exercise option either (a) or (b)