In case of anticipatory breach, the aggrieved party may treat the contract; |
A. | As discharged and bring an immediate action for damages |
B. | As operative and wait till the time for performance arrives |
C. | Exercise option either (a) or (b) |
D. | None of these |
Answer» C. Exercise option either (a) or (b) |