Q.

A feasible solution is called a basic feasible solution if the number of non‐negative allocations is equal to ‐‐‐‐‐‐‐‐‐‐‐‐‐‐

A. m‐n+1
B. m‐n‐1
C. m+n‐1
D. None of the above
Answer» C. m+n‐1