| Q. |
__________ defines when the work is ready for or is being used for the purpose intended and is so certified. |
| A. | Final completion |
| B. | Substantial completion |
| C. | Final acceptance |
| D. | Mechanical completion |
| Answer» B. Substantial completion | |