Q. |
A manager and the head of engineering discuss a change to a major work package. After the meeting, the manager contacts you and tells you to complete the paperwork to make the change. This is an example of: |
A. | Management attention to scope management. |
B. | Management planning. |
C. | A project expediter position. |
D. | A change control system. |
Answer» C. A project expediter position. |