Q. |
In PERT analysis, the time estimates of activities and probability of their occurrence follow |
A. | Normal distribution curve |
B. | Poisson's distribution curve |
C. | Beta distribution curve |
D. | None of the above |
Answer» C. Beta distribution curve |