If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be |
| A. | 50 % |
| B. | Less than 50 % |
| C. | More than 50 % |
| D. | 100 % |
| Answer» C. More than 50 % | |