If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be |
A. | 50 % |
B. | Less than 50 % |
C. | More than 50 % |
D. | 100 % |
Answer» C. More than 50 % |