McqMate
| Q. |
Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is |
| A. | 20 |
| B. | 25 |
| C. | 35 |
| D. | 15 |
| Answer» B. 25 | |
View all MCQs in
Construction ManagementNo comments yet