McqMate
Q. |
Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is |
A. | 20 |
B. | 25 |
C. | 35 |
D. | 15 |
Answer» B. 25 |
View all MCQs in
Construction ManagementNo comments yet