If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be

A. to + 3tm+ tp/3
B. to + 4tm+ tp/4
C. to + 4tm+ tp/5
D. to + 4tm+ tp/6
Answer» D. to + 4tm+ tp/6