The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is |
| A. | 19 |
| B. | 14 |
| C. | 24 |
| D. | None of these |
| Answer» A. 19 | |
View all MCQs in