Q.

In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having

A. Longest duration
B. Highest cost slope
C. Least cost slope
D. Shortest duration
Answer» C. Least cost slope
1.7k
0
Do you find this helpful?
16

View all MCQs in

Construction Management

Discussion

AKN

Aniruddh Kumar Nayak
3 weeks ago

Appreciate the MCQs, they're outstanding.
1