In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having |
| A. | Longest duration |
| B. | Highest cost slope |
| C. | Least cost slope |
| D. | Shortest duration |
| Answer» C. Least cost slope | |