McqMate
Q. |
Consider the following statements: In the bar chart planning 1. Interdependence of the operations cannot be portrayed. 2. Progress of work can be measured. 3. Spare time of the activities can be determined. 4. Schedule cannot be updated. Of these statements |
A. | 1, 2 and 3 are correct |
B. | 1 and 4 are correct |
C. | 2, 3 and 4 are correct |
D. | 1, 2 and 4 are correct |
Answer» B. 1 and 4 are correct |
View all MCQs in
Construction ManagementNo comments yet