McqMate
| Q. |
Consider the following operations: 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete The correct sequence of these operations in tunnel construction is |
| A. | 1, 2, 4, 3, 5 |
| B. | 1, 3, 2, 4, 5 |
| C. | 1, 2, 3, 4, 5 |
| D. | 1, 3, 4, 2, 5 |
| Answer» C. 1, 2, 3, 4, 5 | |
View all MCQs in
Construction ManagementNo comments yet