Q.

Consider the following operations: 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete The correct sequence of these operations in tunnel construction is

A. 1, 2, 4, 3, 5
B. 1, 3, 2, 4, 5
C. 1, 2, 3, 4, 5
D. 1, 3, 4, 2, 5
Answer» C. 1, 2, 3, 4, 5