Crash project duration is obtained by summing the |
| A. | Normal durations for all the activities |
| B. | Crash durations for all activities |
| C. | Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities |
| D. | Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities. |
| Answer» D. Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities. | |