If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be |
A. | 2.3% and 84.1% |
B. | 97.7% and 84.1% |
C. | 97.7 % and 15.9% |
D. | 15.9% and 97.7% |
Answer» A. 2.3% and 84.1% |