Preliminary project report for a road project must contain |
A. | The detailed estimated cost based on detailed design |
B. | The several alternatives of the project that have been considered |
C. | The soil survey, traffic survey, concept design and approximate cost |
D. | The contract documents for inviting tenders |
Answer» C. The soil survey, traffic survey, concept design and approximate cost |