A pile is being driven with a drop hammer weighing 1800 kg and having a free fall of 1.00 m. If the penetration with last blow is 5 mm, the load carrying capacity of the pile, -according to the Engineering News formula, is |
A. | 100 tonnes |
B. | 50 tonnes |
C. | 20 tonnes |
D. | 10 tonnes |
Answer» D. 10 tonnes |