Pessimistic time is |
| A. | The maximum time which an activity might require |
| B. | The average time required for a job |
| C. | The time which has the highest probability of occurrence associated with it |
| D. | The minimum time in which an activity can possibly be accomplished |
| E. | The earliest possible time that an event can be reached or an activity completed. |
| Answer» A. The maximum time which an activity might require | |