McqMate
These multiple-choice questions (MCQs) are designed to enhance your knowledge and understanding in the following areas: Bachelor of Commerce (B Com) .
1. |
In job costing each ………. Is a cost unit to which all costs are assigned |
A. | Jobb |
B. | profit |
C. | Batch |
D. | cost |
Answer» A. Jobb |
2. |
In a contract costing most of the items of cost are …………….. |
A. | Indirect |
B. | direct |
C. | normal |
D. | fixed |
Answer» B. direct |
3. |
……………. In a contract , provides that the contract price would be suitably enhanced on the happening of a specified contingency |
A. | Cost plus contract |
B. | estimated profit |
C. | Escalation\ clause |
D. | EBQ |
Answer» C. Escalation\ clause |
4. |
The loss incurred on an incomplete contract is transferred to ……… account |
A. | Profit & loss a/c |
B. | work in progress |
C. | depreciation |
D. | Machinery |
Answer» A. Profit & loss a/c |
5. |
When the completion stage of the contract is more than half, the profit to be credited to P/L a/c will be equal to ……………….. |
A. | 2/3 *notional profit *CR/WC |
B. | Estimated profit *W.C/contract price |
C. | 1/3 * N.P * CR/W.C |
D. | Total profit |
Answer» A. 2/3 *notional profit *CR/WC |
6. |
In …………….. contract the contractor will get cost plus stipulated profit |
A. | Sub contract |
B. | cost plus contract |
C. | job |
D. | direct |
Answer» B. cost plus contract |
7. |
Scope of specific order costing is very wide and includes ……. ,………, …………. |
A. | Job, Batch and contract costing |
B. | Process , Contract and unit costing |
C. | Batch , Job and process costing |
D. | Unit , service and transport costing |
Answer» A. Job, Batch and contract costing |
8. |
………… is an important point to be determined in industries where batch costing is employed |
A. | EBQ |
B. | EOQ |
C. | Re – order quantity |
D. | Batch |
Answer» A. EBQ |
9. |
When a contract is debited with the original cost of the plant , it should credited with ………… at the end of the year |
A. | Original cost of the plant |
B. | Depreciated value of the stock |
C. | Profit |
D. | Estimated cost |
Answer» B. Depreciated value of the stock |
10. |
When the competition stage of a contract is less than ¼ , the total expenditure on the contract is transferred to ………… account |
A. | Work in progres |
B. | P/L a/c |
C. | Estimated profit |
D. | Notional profit |
Answer» A. Work in progres |
11. |
If the contract is almost complete , the amount of profit generally transferred to profit and loss account is equal to |
A. | Estimated profit * work certified/ contract price |
B. | Estimated profit * contract price / work certified |
C. | Notional profit * C.R/ W.C |
D. | Notional profit W.C/ C.R |
Answer» A. Estimated profit * work certified/ contract price |
12. |
In a contract costing payment of cash to the contract is made on the basis of …………………………. Work |
A. | Certified |
B. | profit and loss a/c |
C. | contract price |
D. | cost |
Answer» A. Certified |
13. |
Job costing is applied only in …………………. Concern |
A. | Small |
B. | large |
C. | medium |
D. | None of these |
Answer» A. Small |
14. |
Contract costing is a basic method of …………….. costing |
A. | Specific order costing |
B. | batch costing |
C. | process costing |
D. | Unit costing |
Answer» A. Specific order costing |
15. |
In job costing the production is generally against customers …………………. but not for stock |
A. | Order |
B. | profit |
C. | cash in hand |
D. | none of these |
Answer» A. Order |
16. |
The method of costing applied in biscuit industries is ……………………. |
A. | Jo |
B. | process |
C. | contract |
D. | unit |
Answer» A. Jo |
17. |
Average unit cost for each process is calculated by dividing ……………..by ……………. |
A. | Total process cost / No.of units in process |
B. | Total process cost / Total cost |
C. | Total cost / Total profit |
D. | None of these |
Answer» A. Total process cost / No.of units in process |
18. |
Where raw material is to pass certain stages before it is converted into finished goods, the method of costing used is …………………… |
A. | Contract |
B. | Process |
C. | unit |
D. | Batch |
Answer» B. Process |
19. |
When the actual loss is more than the estimated loss, the difference between the two is considered to be ,…………………. |
A. | Abnormal gain |
B. | Abnormal loss |
C. | Normal loss |
D. | Normal gain |
Answer» B. Abnormal loss |
20. |
……………….. process loss should be transferred to costing profit and loss account |
A. | Normal |
B. | abnormal |
C. | actual |
D. | none of these |
Answer» B. abnormal |
21. |
The cost of ……….. process loss is absorbed in the cost of production of good units |
A. | Normal |
B. | abnormal |
C. | actual |
D. | none of these |
Answer» A. Normal |
22. |
Where actual loss in a process is less than the anticipated loss , the difference b/w the two is considered to be ………….. |
A. | Normal los |
B. | Abnormal gain |
C. | normal gain |
D. | None of |
Answer» B. Abnormal gain |
23. |
……… is the difference b/w the sales and marginal cost of sale |
A. | Profit |
B. | contribution |
C. | p/v ratio |
D. | none f these |
Answer» B. contribution |
24. |
Cost of producing an additional unit of output is …………… |
A. | Historical cost |
B. | marginal cost |
C. | fixed cost |
D. | total cost |
Answer» B. marginal cost |
25. |
A cost do not change with changes in the level of activity is …………. |
A. | Variable cost |
B. | fixed cost |
C. | sunk cost |
D. | total cost |
Answer» B. fixed cost |
26. |
A cost both containing both fixed and variable elements ……………….. |
A. | Variable cost |
B. | fixed cost |
C. | total cost |
D. | semi variable cost |
Answer» C. total cost |
27. |
The excess of sales over variable cost is known as ……………… |
A. | profit |
B. | loss |
C. | contribution |
D. | margin |
Answer» C. contribution |
28. |
Establishes the relationship between cost , volume of sales and profit is ….. |
A. | Marginal costing |
B. | standard costing |
C. | budgeting |
D. | Cost volume profit analysis |
Answer» D. Cost volume profit analysis |
29. |
A point at which there is neither profit nor loss ……………… |
A. | No profit no loss point |
B. | Break even point |
C. | Margin of safety |
D. | contribution |
Answer» B. Break even point |
30. |
Excess of sales over break even sales is known as ………………….. |
A. | No profit no loss point |
B. | Breakeven point |
C. | Margin of safety |
D. | contribution |
Answer» C. Margin of safety |
31. |
The angle formed at the point of incidence of sales line to total cost……. |
A. | Angle of incidence |
B. | break even point |
C. | Fixed cost |
D. | total cost |
Answer» A. Angle of incidence |
32. |
A factor that restrict the activities of a concern …………….. |
A. | Contribution factor |
B. | break even point |
C. | Key factor |
D. | margin of safety |
Answer» C. Key factor |
33. |
…….. is method of cost volume profit analysis |
A. | Budgeting |
B. | budgetary control |
C. | Standard costing |
D. | break even analysis |
Answer» D. break even analysis |
34. |
The additional cost of producing an additional unit is called ………. |
A. | Fixed cost |
B. | marginal cost |
C. | Semi variable |
D. | none of these |
Answer» B. marginal cost |
35. |
Variable cost can also be called as ………………………… |
A. | Semi variable |
B. | marginal cost |
C. | Standard costing |
D. | fixed cost |
Answer» B. marginal cost |
36. |
Break even units can also be called as ……………………… |
A. | Break even output |
B. | break even sales |
C. | Margin of safety |
D. | contribution |
Answer» A. Break even output |
37. |
Sales – variable cost = …………………………………….. |
A. | Marginal cost |
B. | fixed cost |
C. | Budget cost |
D. | contribution |
Answer» D. contribution |
38. |
Excess of actual sales over break even sales is ………………… |
A. | Break even unit |
B. | angle of incidence |
C. | Margin of safety |
D. | contribution |
Answer» C. Margin of safety |
39. |
The angle formed were the total cost line under sects the sale line is |
A. | Angle of incidence |
B. | margin of safety |
C. | Breakeven point |
D. | contribution |
Answer» A. Angle of incidence |
40. |
The cost which varies proportionate to increase in production is …….. cost |
A. | Fixed |
B. | variable cost |
C. | Semi variable cost |
D. | break even cost |
Answer» B. variable cost |
41. |
The cost which remains constant with change in level of activities is called |
A. | Variable cost |
B. | marginal cost |
C. | Standard cost |
D. | fixed cost |
Answer» D. fixed cost |
42. |
……………….. is an angle formed in break even chart |
A. | Margin of safety |
B. | angle of incidence |
C. | Contribution |
D. | Break even point |
Answer» B. angle of incidence |
43. |
…………… is a graphical representation of marginal costing |
A. | Break even chart |
B. | angle of incidence |
C. | Margin of safety |
D. | none of these |
Answer» A. Break even chart |
44. |
Contract price is fixed in advance |
A. | Cost plus contract |
B. | Target costing |
C. | Fixed price contract |
D. | Fluctuating contract |
Answer» C. Fixed price contract |
45. |
Contract price is the cost of work done plus a percentage |
A. | Cost plus contract |
B. | target costing |
C. | Fixed price contract |
D. | fluctuating contract |
Answer» A. Cost plus contract |
46. |
Value of work done to the satisfaction of contractee |
A. | Work certified |
B. | Work un certified |
C. | Fixed price contract |
D. | fluctuating contract |
Answer» B. Work un certified |
47. |
A portion of work certified retained by contractee is known |
A. | Retention money |
B. | advance |
C. | Fixed price contract |
D. | fluctuating contract |
Answer» A. Retention money |
48. |
Profit on incomplete contract is known as ,……….. |
A. | P/L a/c |
B. | notional profit |
C. | Net profit |
D. | completed contract |
Answer» B. notional profit |
49. |
Work in the process of completion |
A. | Work in progres |
B. | notional profit |
C. | Net profit |
D. | completed contract |
Answer» A. Work in progres |
50. |
A portion of main contract entrusted to some one else |
A. | Extra work |
B. | Sub work |
C. | Work in progress |
D. | Sub contract |
Answer» D. Sub contract |
Done Studing? Take A Test.
Great job completing your study session! Now it's time to put your knowledge to the test. Challenge yourself, see how much you've learned, and identify areas for improvement. Don’t worry, this is all part of the journey to mastery. Ready for the next step? Take a quiz to solidify what you've just studied.