Identify the given type of joint in Concrete Structures. |
| A. | l beam construction joint |
| B. | t beam construction joint |
| C. | expansion joint |
| D. | contraction joint |
| Answer» B. t beam construction joint | |
| Explanation: in case of t-beams, the ribs should be filled with concrete first and in the slabs forming the flanges can be filled up to the centre of the ribs. if a construction joint between slab and beam becomes unavoidable | |