151.

An event is indicated on the network by a number enclosed in

A. A circle
B. A square
C. A triangle
D. All the above
Answer» D. All the above
152.

Select the incorrect statement.

A. A critical path always begins at the very first event.
B. A critical path always terminates at the last event.
C. Critical activities control the project duration.
D. Critical activity is the one for which free float is zero.
Answer» D. Critical activity is the one for which free float is zero.
153.

If t is the duration of an activity, t1 is the latest finish possible moment of its preceding activity and t2 is the earliest start possible moment, the independent float of the activity is

A. (t1 - t2) - t
B. t - (t1 - t2)
C. (t1 + t2) - t
D. t + (t1 - t2)
Answer» A. (t1 - t2) - t
154.

Free float for any activity is defined as the difference between

A. Its earliest finish time and earliest start time for its successor activity
B. Its latest start time and earliest start time
C. Its latest finish time and earliest start time for its successor activity
D. Its earliest finish time and latest start time for its successoractivity
Answer» A. Its earliest finish time and earliest start time for its successor activity
155.

In CPM analysis,

A. Emphasis is given to activities
B. Uncertainties are not allowed
C. Activities are represented by arrows
D. All the above
Answer» D. All the above
156.

The estimated time required to perform an activity, is known as

A. Event
B. Dummy
C. Duration
D. Float
Answer» C. Duration
157.

Critical Path Net Work helps an engineer

A. To concentrate his attention on critical activities
B. To divert the resources from non-critical advanced activities to critical activities
C. To be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
D. All the above
Answer» D. All the above
158.

B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he

A. Should invest in neither of the two projects
B. Could invest in either of the two projects
C. Should invest in project A
D. Should invest in project B
Answer» A. Should invest in neither of the two projects
159.

Henry Gantt developed Bar charts for planning and scheduling of projects in

A. 1880
B. 1900
C. 1920
D. 1940
Answer» B. 1900
160.

If TL is the latest allowable event occurrence time, total activity slack(s), is equal to

A. LST-EST
B. LFT-EFT
C. TL-EFT
D. All the above
Answer» D. All the above
161.

Modular co-ordination of construction means proper

A. Planning
B. Designing
C. Execution
D. All the above
Answer» D. All the above
162.

Pick up the correct statement from the following:

A. CPM analysis is activity oriented
B. PERT analysis is event oriented
C. In CPM, the time is related to cost
D. All the above
Answer» D. All the above
163.

The final selection of a construction site, is done by

A. Departmental representative or user
B. Local civil authority representative
C. Representative of engineer authority
D. All the above
Answer» D. All the above
164.

The main advantage of line organisation is:

A. Effective command and control
B. Rigid discipline in the organisation
C. Defined responsibilities at all levels
D. All the above
Answer» D. All the above

Done Studing? Take A Test.

Great job completing your study session! Now it's time to put your knowledge to the test. Challenge yourself, see how much you've learned, and identify areas for improvement. Don’t worry, this is all part of the journey to mastery. Ready for the next step? Take a quiz to solidify what you've just studied.