Select the incorrect statement. |
| A. | A critical path always begins at the very first event. |
| B. | A critical path always terminates at the last event. |
| C. | Critical activities control the project duration. |
| D. | Critical activity is the one for which free float is zero. |
| Answer» D. Critical activity is the one for which free float is zero. | |