Q. |
Select the incorrect statement. |
A. | A critical path always begins at the very first event. |
B. | A critical path always terminates at the last event. |
C. | Critical activities control the project duration. |
D. | Critical activity is the one for which free float is zero. |
Answer» D. Critical activity is the one for which free float is zero. |