

McqMate
Q. |
In the project environment, the individual ultimately responsible for quality control is: |
A. | The line workers who must strive "to do things right the first time" to avoid quality problems |
B. | The company's quality control manager who must work with the project members to ensure the quality control program is effective |
C. | The head of the production department who retains ultimate quality control responsibility for all the company's projects |
D. | The project manager who has ultimately responsibility for the entire project |
Answer» D. The project manager who has ultimately responsibility for the entire project |
View all MCQs in
Total Quality Management (TQM)No comments yet