McqMate
Q. |
The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as |
A. | Duration |
B. | Total float |
C. | Free float |
D. | Interfering float |
Answer» C. Free float |
View all MCQs in
Construction ManagementNo comments yet