Q.

If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is

A. (a + m + b)/6
B. (a + 2m + b)/6
C. (a + 4m + b)/6
D. (a + 5m + b)/6
Answer» C. (a + 4m + b)/6