Q.

If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is

A. (a + m + b)/6
B. (a + 2m + b)/6
C. (a + 4m + b)/6
D. (a + 5m + b)/6
Answer» C. (a + 4m + b)/6
1k
0
Do you find this helpful?
1

View all MCQs in

Construction Management

Discussion

No comments yet

Related MCQs