If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is |
| A. | (a + m + b)/6 |
| B. | (a + 2m + b)/6 |
| C. | (a + 4m + b)/6 |
| D. | (a + 5m + b)/6 |
| Answer» C. (a + 4m + b)/6 | |