Civil Engineering
→
Construction Management
→
The direct cost of a project with respec...
Q.
The direct cost of a project with respect to normal time is
A.
minimum
B.
Maximum
C.
Zero
D.
Infinite
Answer» A. minimum
1.4k
0
Do you find this helpful?
6
View all MCQs in
Construction Management
Discussion
No comments yet
Login to comment
Related MCQs
If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be
Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is
If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is
The time with which direct cost does not reduce with the increase in time is known as
If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is
If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be
In time-cost optimization of a project, crashing is done.
The time corresponding to minimum total project cost is
If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is
Preliminary project report for a road project must contain