Q.

Mobilization advance up to 10% of the cost of work is given to a contractor

A. On commencement of work at site for payment of loan taken by him
B. For the purchase of construction materials
C. For the payment of advances to labour and otherstaff
D. For all activities required to start the work at site on finalization of the contract document
Answer» D. For all activities required to start the work at site on finalization of the contract document
1.5k
0
Do you find this helpful?
4

View all MCQs in

Construction Management

Discussion

No comments yet

Related MCQs