Project managers often work 10 or more hours per day to fit the many activities into their professional schedule. There is a general agreement that all the professional time is not used as efficiently as possible. the major consumer of time, nearly two hours per day, is __________. |
A. | talking to top management |
B. | visiting the customer |
C. | attending project meetings |
D. | . writing reports. |
Answer» C. attending project meetings |