

McqMate
Q. |
Pick up the correct statement from the following: |
A. | The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float' |
B. | The duration of time by which an activity can be delayed without affecting the succeeding activity, is called free float |
C. | The difference between total float and free float, is called interfering float |
D. | All the above |
Answer» D. All the above |
View all MCQs in
Construction ManagementNo comments yet