Pick up the correct statement from the following: |
| A. | Forward pass is used for calculating earliest expected time |
| B. | Backward pass is used for calculating the latest occurrence time |
| C. | Maximum value of earliest expected time is used if there is more than one value ofany event |
| D. | All the above |
| Answer» D. All the above | |