Q. |
Pick up the correct statement from the following: |
A. | The float may be positive, zero or negative |
B. | If the float is positive and the activity is delayed by a period equal to its total float, the completion of project is not delayed |
C. | If the float of an activity is negative, delay in its performance is bound to delay the completion of project |
D. | All the above |
Answer» D. All the above |