Pick up the incorrect statement from the following: |
| A. | The activity is the time consuming part of a project |
| B. | The beginning and end of a job, are called events |
| C. | The activity which consumes maximum time, is called a node |
| D. | Logically and sequentially connected activities and events form a network |
| Answer» C. The activity which consumes maximum time, is called a node | |