McqMate
| Q. |
Pick up the correct statement from the following with regards to C.P.M. network analysis of projects |
| A. | The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest starttime |
| B. | The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time |
| C. | Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity |
| D. | All the above |
| Answer» D. All the above | |
View all MCQs in
Construction ManagementNo comments yet