Pick up the correct statement from the following: |
| A. | Earliest expected time is denoted by TE |
| B. | Latest occurrence time is denoted by TL |
| C. | Contractual obligation time is denoted by Ts |
| D. | All the above |
| Answer» D. All the above | |