Assertion (A): Activity 57 is critical. Reason (R): Earliest finish time and latest finish time for events 57 are same Select the correct answer. |
A. | A is correct but R is not correct |
B. | R is correct but A is not correct |
C. | Both A and R is correct |
D. | Both A and R is incorrect |
Answer» A. A is correct but R is not correct |