Q.

The technique for establishing and maintaining priorities among the various jobs of a project, is known

A. Event flow scheduling technique
B. Critical ratio scheduling
C. Slotting technique forscheduling
D. Short interval scheduling
Answer» B. Critical ratio scheduling