| Q. |
If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively |
| A. | 3.5 and 5/6 |
| B. | 5 and 25/36 |
| C. | 3.5 and 25/36 |
| D. | 4 and 5/6 |
| Answer» C. 3.5 and 25/36 | |