Q.

The maximum continuous power available from a hydro-electric plant under the most adverse hydraulic conditions is known as

A. Primary power
B. Firm power
C. Installed capacity
D. Base power
E. Secondary power
Answer» B. Firm power
1.5k
0
Do you find this helpful?
8

Discussion