Q.

First coat of bituminous painting shall be with stone ballast no.3 and stone grit of 20 mm gauge at 220 kg of asphalt and 1.35 cu m of stone grit per 100 sq. m.

A. true
B. false
Answer» B. false
Explanation: first coat of bituminous painting shall be with asphalt or road tar no.3 and stone grit of 20 mm gauge at 220 kg of asphalt and 1.35 cu m of stone grit per 100 sq. m.