480+ Cost Accounting Solved MCQs

201.

When the completion stage of a contract is less than ¼, the total expenditure on the contract is transferred to ………………..account.

A. Work-in-Progress
B. Profit and loss account
C. miscellaneous account
D. none of these
Answer» A. Work-in-Progress
202.

If the amount of work certified is less than………of the contract price, then no profit should be taken to Profit & Loss Account.

A. 20%
B. 25%
C. 33 1/3%
D. 40%
Answer» B. 25%
203.

Contract costing is not used in one of the following industries.

A. Ship building
B. Civil Construction
C. Automobiles
D. Construction of Bridges
Answer» C. Automobiles
204.

The sum of value of work certified and uncertified appearing in the Contract Account is called ……………..

A. Work in Progress
B. Work in Process
C. Work Completed
D. Work done.
Answer» A. Work in Progress
205.

……………………is the most suitable method in a transport industry.

A. Operation costing
B. Service costing
C. Process costing
D. Job costing
Answer» B. Service costing
206.

Room/day is the cost unit used in…………………

A. Hotels
B. hospital
C. schools
D. none of these
Answer» A. Hotels
207.

Maintenance charges are in the nature of …………………expenses.

A. Fixed
B. Variable
C. semi-variable
D. none of these
Answer» C. semi-variable
208.

In transport costing………………charges vary more or less in direct proportion to kilometers run.

A. Running
B. petrol
C. drivers salary
D. tax
Answer» A. Running
209.

Service costing is called as ……………….

A. Operation costing
B. Operating costing
C. multiple costing
D. none of these
Answer» B. Operating costing
210.

In electricity supply company uses …………….as cost unit.

A. Kilo watt hour
B. per household
C. voltage
D. none of these
Answer» A. Kilo watt hour
211.

In transportation costing a composite unit such as …………….is used.

A. passenger mile/km or Ten kilometer
B. per km
C. per passenger
D. per stop
Answer» A. passenger mile/km or Ten kilometer
212.

Boiler house costing is an example of …………….costing

A. Operation
B. process
C. service
D. none of these
Answer» C. service
213.

In service costing, fixed charges are also called as…………………..

A. Standing charges
B. variable charges
C. fixed charges
D. none of these
Answer» A. Standing charges
214.

Service costing is not used in one of the following:

A. Electricity
B. Hospitals
C. transport
D. Electronics
Answer» D. Electronics
215.

If the present cost of the car is Rs.1,00,000 residual value at the end of the 5th year is Rs.20,000, the monthly depreciation is…………

A. Rs.20,000
B. Rs.16,000
C. Rs.1,333
D. Rs.17,333
Answer» C. Rs.1,333
216.

A bus carries 25 passengers daily for 25 days and its mileage per month is 1000 kms. Its passenger miles are………………

A. 30,000
B. 12,500
C. 20,000
D. 25,000
Answer» D. 25,000
217.

In ……………………costing where standardized goods or services result from a sequence of repetitive and more or less continuous operations to which costs are collected and averaged over the units produced during the year:

A. Multiple
B. Process
C. Operation
D. single.
Answer» C. Operation
218.

The method of costing applied in biscuit industries is ………….costing and in steel industry………….costing.

A. Job, process
B. job, contract
C. batch, multiple
D. process, operation
Answer» A. Job, process
219.

Average unit cost for each process is calculated by dividing the ………………..by…………………

A. Total cost, number of units
B. total process cost, number of units in process
C. Total process cost, number of finished goods
D. total cost, number of units produced
Answer» B. total process cost, number of units in process
220.

Where raw material is to pass certain stages, before it is converted into finished goods, the method of costing used is…………………

A. Job costing
B. Operating costing
C. Process Costing
D. both b and c
Answer» C. Process Costing
221.

When the actual loss is more than the estimated loss, the difference between the two is considered to be………..

A. Abnormal loss
B. normal loss
C. loss
D. none of these
Answer» A. Abnormal loss
222.

When actual loss is less than the estimated loss, the difference between the two is considered to be……………

A. Abnormal gain
B. abnormal loss
C. normal loss
D. income
Answer» A. Abnormal gain
223.

When actual loss is ………..than the estimated loss, the difference between the two is considered to be abnormal gain

A. More
B. less
C. higher
D. none of these
Answer» B. less
224.

When actual loss is ………………than the estimated loss, the difference between the two is considered to be abnormal loss.

A. More
B. less
C. both a & b)
D. none of these
Answer» A. More
225.

When 1000 units are 60% complete in a process, it is equivalent to …………….completed units.

A. 60
B. 600
C. 6000
D. 1000
Answer» B. 600
226.

Equivalent units represent the production of a process in terms of ………..units.

A. Completed
B. total production
C. semi-finished
D. both a& c
Answer» A. Completed
227.

…………..process loss should be transferred to costing profit & loss account.

A. Abnormal
B. normal
C. both a& b
D. none of these
Answer» A. Abnormal
228.

The cost of …………..process loss is absorbed in the cost of production of good units.

A. Abnormal
B. normal
C. both a & b
D. none of these
Answer» B. normal
229.

In inter process profits, the output of one process is transferred from one process to another not at …………….but at ……………….

A. Market price, actual cost
B. Actual cost, market price
C. both a& b
D. none of these
Answer» B. Actual cost, market price
230.

Where actual loss in a process is less than the anticipated loss, the difference between the two is considered to be ………………..

A. Abnormal loss
B. normal loss
C. abnormal gain
D. normal gain
Answer» C. abnormal gain
231.

In process costing, the abnormal loss is treated as ……….cost and written off to profit & loss account.

A. Unit
B. period
C. future
D. process
Answer» B. period
232.

The process costing is not used in one of the following.

A. Chemical
B. textiles
C. cement
D. oil refining
Answer» C. cement
233.

………….arises where the actual process loss is less than the normal predetermined process loss.

A. Normal loss
B. abnormal loss
C. abnormal gain
D. none of these
Answer» C. abnormal gain
234.

An input of 5000kg of material introduced into the process and the expected loss is 8% and if the actual output from the process is 4300, the abnormal loss is …………kg

A. 400
B. 300
C. 500
D. 600
Answer» B. 300
235.

Budgeting system……………key managerial functions.

A. Dismisses
B. integrates
C. discharges
D. none of these
Answer» B. integrates
236.

…………………is a budget which is updated continuously by adding a further period (a month/quarter) and deducting a corresponding earlier period.

A. Rolling budget
B. continuous budget
C. annual budget
D. both a & b
Answer» D. both a & b
237.

The budget relating to ………….must be prepared first and the other budgets should be prepared in the light of that factor.

A. Limiting factor
B. materials
C. labour
D. production
Answer» A. Limiting factor
238.

…………………budget is the most important budget and it forms the basis on which all the other budgets are built up.

A. Production
B. material
C. cash budget
D. sales
Answer» D. sales
239.

………………….budget may be classified into material cost budget, labour cost budget and overhead budget.

A. Cost of Production
B. purchase
C. sales
D. Cash
Answer» A. Cost of Production
240.

……………….budget gives an estimate of the anticipated receipts and payment of cash during the budget period.

A. Sales
B. Production
C. Cash
D. Master
Answer» C. Cash
241.

……………….is the consolidated summary of the various functional budgets.

A. Master Budget
B. Sales budget
C. Performance budget
D. Cash Budget
Answer» A. Master Budget
242.

…………………budget is designed to remain unchanged irrespective of the volume of output or turnover attained.

A. Master
B. Fixed
C. Flexible
D. all of these
Answer» B. Fixed
243.

…………………budget gives differentbudgeted costs for different levels of activity.

A. Master
B. Fixed
C. Flexible
D. all of these
Answer» C. Flexible
244.

…………………budget is the preparation of budget starting from a clean state.

A. Performance
B. Zero Base
C. Cash
D. none of these
Answer» B. Zero Base
245.

Calendar Ratio =

A. Number of actual working days in a period x 100 Number of working days in the budget period
B. Actual hours worked x 100 Budgeted hours
C. Standard hours for actual production x 100 Actual hours worked
D. Standard hours for actual productionx 100 Budgeted standard hours
Answer» A. Number of actual working days in a period x 100 Number of working days in the budget period
246.

Capacity Ratio =

A. Number of actual working days in a period x 100 Number of working days in the budget period
B. Actual hours worked x 100 Budgeted hours
C. Standard hours for actual production x 100 Actual hours worked
D. Standard hours for actual productionx 100 Budgeted standard hours
Answer» B. Actual hours worked x 100 Budgeted hours
247.

Efficiency Ratio=

A. Number of actual working days in a period x 100 Number of working days in the budget period
B. Actual hours worked x 100 Budgeted hours
C. Standard hours for actual production x 100 Actual hours worked
D. Standard hours for actual productionx 100 Budgeted standard hours
Answer» C. Standard hours for actual production x 100 Actual hours worked
248.

Activity Ratio =

A. Number of actual working days in a period x 100 Number of working days in the budget period
B. Actual hours worked x 100 Budgeted hours
C. Standard hours for actual production x 100 Actual hours worked
D. Standard hours for actual productionx 100
Answer» D. Standard hours for actual productionx 100
249.

……………….is a summary of all function budgets in a Capsule form.

A. Master Budget
B. Sales budget
C. Performance budget
D. Cash Budget
Answer» A. Master Budget
250.

……………..determines the priorities of functional budget.

A. Principal Budget Factor
B. Limiting Factor
C. both a & b
D. none of the above.
Answer» C. both a & b
251.

Cash Budget is a ……………….budget.

A. Long term
B. very long term
C. short term
D. very short term
Answer» C. short term
252.

The primary difference between a fixed budget and a variable(flexible) budget is that a fixed budget:

A. Includes only fixed costs, while a variable budget includes only variable costs.
B. Is concerned only with future acquisitions of fixed assets, while a variable budget is concerned with expenses which vary with sales.
C. Cannot be changed after the period begins, while a variable budget can be changed after the period begins.
D. Is a plan for a single level of sales(or other measure of activity), while a variable budget consists of several plans, one for each of several levels of sales (or other measure of activity)
Answer» D. Is a plan for a single level of sales(or other measure of activity), while a variable budget consists of several plans, one for each of several levels of sales (or other measure of activity)
253.

Sales budget is a

A. Functional budget
B. Master budget
C. Expenditure budget
D. none of these
Answer» A. Functional budget
254.

In the case of plant, the limiting factor may be:

A. Insufficient capacity
B. shortage of experienced salesmen
C. general shortage of power
D. shortage of materials
Answer» A. Insufficient capacity
255.

The difference between fixed and variable cost has a special significance in the preparation of

A. Flexible budget
B. master budget
C. cash budget
D. sales budget
Answer» A. Flexible budget
256.

The budget that is prepared first of all is…………..

A. Cash budget
B. master budget
C. budget for the key factor
D. sales budget
Answer» C. budget for the key factor
257.

In case of materials the key factor may be.

A. Insufficient advertising
B. restrictions imposed by quota
C. low market demand
D. shortage of power
Answer» B. restrictions imposed by quota
258.

The budget which commonly takes the form of budgeted profit and loss account and balance sheet is

A. cash budget
B. master budget
C. flexible budget
D. fixed budget
Answer» B. master budget
259.

Standard cost is a …………..cost

A. Predetermined
B. historical
C. actual
D. final
Answer» A. Predetermined
260.

The limitations of …………………………has led to the development of standard costing system.

A. Historical costing system
B. cost accounting
C. management accounting
D. none of these
Answer» A. Historical costing system
261.

Standard costing is more widely applied in…………………industries.

A. Process and engineering
B. jobbing industries
C. construction industry
D. all of these
Answer» A. Process and engineering
262.

Three types of standards are…………..

A. Current standard, basic standard and normal standard
B. Currency standard, basel standard and actual standard
C. Actual standard, estimated standard and expected standard
D. Expected standard, ideal standard and current standard
Answer» A. Current standard, basic standard and normal standard
263.

The deviation of the actual cost or profit or sales from the standard cost or profit or sale is known as …………

A. Difference
B. Variance
C. Discrepancy
D. Inconsistency
Answer» B. Variance
264.

Management by exception is exercising control over………..

A. Costs
B. Favourable items
C. Unfavourable items
D. all of these
Answer» C. Unfavourable items
265.

Material price variance is the difference between standard and actual prices of materials used multiplied by………………..

A. Actual quantity of materials used
B. Budgeted quantity of materials used
C. Standard quantity of materials used
D. Either a or b
Answer» A. Actual quantity of materials used
266.

Labour cost variance is the difference between standard cost of labour and………..

A. Budgeted cost of labour
B. Estimated cost of labour
C. Actual cost of labour
D. None of these
Answer» C. Actual cost of labour
267.

Idle time variance is………….

A. Idle time x actual labour
B. Idle time x standard rate
C. Idle time x budgeted labour rate
D. Idle time x historical cost
Answer» B. Idle time x standard rate
268.

Volume variance is divided into……………

A. Capacity variance, calendar variance andExpenditure variance
B. Capacity variance, calendar variance and efficiency variance
C. Capacity variance, expenditure variance and efficiency variance
D. Calendar variance, expenditure variance and efficiency variance
Answer» B. Capacity variance, calendar variance and efficiency variance
269.

Standards set provide yardsticks against which………….are compared.

A. Budgeted costs
B. Estimated costs
C. Actual costs
D. None of these
Answer» C. Actual costs
270.

The technique of standard costing may not be applicable in case of

A. Large concerns
B. Small concerns
C. All concerns
D. Both b & c
Answer» D. Both b & c
271.

Total Material cost variance =

A. Standard cost of materials-actual cost of materials
B. Budgeted cost of materials- actual cost of materials
C. Standard cost of materials-budgeted cost of materials
D. Actual cost of materials- budgeted cost of materials
Answer» A. Standard cost of materials-actual cost of materials
272.

Material Usage Variance=Material Mix Variance +…………..

A. Material Yield Variance
B. Material cost variance
C. Material price variance
D. Material quantity variance
Answer» A. Material Yield Variance
273.

Material Price Variance = Actual Usage (……………)

A. Standard price
B. Standard unit price-actual unit price
C. Actual price
D. Standard usage
Answer» B. Standard unit price-actual unit price
274.

Material usage variance = standard price(……………….)

A. Standard usage-actual usage
B. Standard unit price-actual unit price
C. Standard quantity
D. Actual quantity
Answer» A. Standard usage-actual usage
275.

Material mix variance = standard cost of standard mix - ………………..

A. Actual cost of actual mix
B. Actual cost of standard mix
C. Standard cost of actual mix
D. Standard cost of budgeted mix
Answer» C. Standard cost of actual mix
276.

Total Labour cost variance =

A. Standard cost of labour - actual cost of labour
B. Standard rate(standard time for actual output-actual time worked)
C. Standard rate (standard time for actual output- actual time paid for)
D. Actual time taken (standard rate-actual rate)
Answer» A. Standard cost of labour - actual cost of labour
277.

Volume Variance =

A. Standard rate (Actual output-budgeted output)
B. Actual output x standard rate-budgeted fixed overheads
C. Standard rate per hour(standard hours produced-actual hours)
D. All of the above
Answer» D. All of the above
278.

A favourable variance will arise when capital revenues are………..than expected.

A. More
B. Less
C. Lesser
D. None of the above
Answer» A. More
279.

An unfavourable material price variance occurs because of:

A. Price increase in raw materials
B. Price decrease in raw materials
C. Less than anticipated normal wastage in the manufacturing process
D. More than anticipated normal wastage in the manufacturing process
Answer» A. Price increase in raw materials
280.

The type of standard best suitable for cost control purpose is

A. Basic standard
B. Ideal standard
C. Normal standard
D. Expected standard
Answer» D. Expected standard
281.

An unfavourable material usage arises because of:

A. Price increase in raw materials
B. Price decrease in raw mateials
C. Less than anticipated normal wastage in the manufacturing process
D. More than anticipated normal wastage in the manufacturing process
Answer» D. More than anticipated normal wastage in the manufacturing process
282.

Volume variance arises because of :

A. Increase in overhead rate per hour
B. Decrease in overhead rate per hour
C. Increase or decrease in actual output as compared to the budgeted output.
D. Difference in budgeted overheads and actual overheads.
Answer» C. Increase or decrease in actual output as compared to the budgeted output.
283.

Labour rate variance is computed by multiplying the

A. Standard labour rate with the difference between standard labour hours and actual labour hours
B. Actual labour hours with the difference between standard labour hours and actual labour hours
C. Actual labour rate with the difference between standard labour rate and actual labour hours.
D. None of the above
Answer» D. None of the above
284.

……………..is an example of long-term budget

A. Cash budget
B. Capital expenditure budget
C. Research and development budget
D. Both b & c
Answer» D. Both b & c
285.

……………..is an example of short-term budget

A. Cash budget
B. Capital expenditure budget
C. Material budget
D. Both a & c
Answer» D. Both a & c
286.

The main objective of cost accounting is:

A. Ascertainment of cost
B. Control of cost
C. Determination of selling price
D. All of the above
Answer» D. All of the above
287.

The expected return or benefit foregone in rejecting one course of action for the other is known as

A. sunk cost
B. opportunity cost
C. conversion cost
D. differential cost
Answer» B. opportunity cost
288.

Costs which are ascertained after they have been incurred are called

A. imputed costs
B. sunk costs
C. historical costs
D. marginal costs
Answer» C. historical costs
289.

A cost centre is

A. a production or service location, function, activity or item of equipment whose costs may be attributed to cost units
B. acentre for which an individual budget is drawn-up
C. acentre where cost is classified on the basis of variability
D. an amount of expenditure attributable to an activity
Answer» A. a production or service location, function, activity or item of equipment whose costs may be attributed to cost units
290.

These accounts are obligatory to be prepared according to the legal requirements of Companies Act and Income Tax Act.

A. Cost Accounting
B. Financial Accounting
C. Management Accounting
D. All of the above
Answer» B. Financial Accounting
291.

The cost unit for a cement industry is

A. Kilogram
B. Dozen
C. Tonne
D. Square foot
Answer» C. Tonne
292.

Hypothetical costs which are specially computed outside the accounting system for the purpose of decision making are called

A. Replacement Cost
B. Imputed Cost
C. Marginal Cost
D. Future Cost
Answer» B. Imputed Cost
293.

Direct material + Directlabour + direct expenses =

A. Prime Cost
B. Works Cost
C. Cost of Production
D. Total Cost
Answer» A. Prime Cost
294.

Costing is a technique of ascertaining: -

A. Cost
B. Profit
C. Loss
D. Standard
Answer» A. Cost
295.

The cost can be controlled by:

A. Standard Costing
B. Budgetary Control
C. Proper presentation
D. All of these
Answer» D. All of these
296.

It is a device for the purpose of breaking up cost into smaller sub-divisions:-

A. Cost Unit
B. Cost Control
C. Cost center
D. Prime cost
Answer» A. Cost Unit
297.

Elements of cost are:-

A. Direct materials
B. Direct labors
C. Overheads
D. All of thesew
Answer» D. All of thesew
298.

These types of costs are partly fixed & partly variable is relation to output:-

A. Fixed Cost
B. Variable Cost
C. Semi-variable Cost
D. Works Cost
Answer» C. Semi-variable Cost
299.

Cost accounting has been developed because of limitation in:-

A. Financial a/c
B. Management a/c
C. Prime Cost
D. None of these
Answer» A. Financial a/c
300.

The cost which is to be incurred even when a business unit is closed is a ____ cost.

A. Imputed
B. Historical
C. Opportunity
D. Shutdown
Answer» D. Shutdown
Tags
Question and answers in Cost Accounting, Cost Accounting multiple choice questions and answers, Cost Accounting Important MCQs, Solved MCQs for Cost Accounting, Cost Accounting MCQs with answers PDF download