97
78k

250+ Management Science Solved MCQs

These multiple-choice questions (MCQs) are designed to enhance your knowledge and understanding in the following areas: Bachelor of Business Administration (BBA) , Master of Commerce (M.com) .

51.

It ………. at which an activity can start.

A. est
B. eft
C. lst
D. lft
Answer» A. est
52.

………… is the earliest starting time plus activity time.

A. est
B. eft
C. lst
D. lft
Answer» B. eft
53.

………. is the latest time by which an activity can be started without delaying the completion of the project.

A. est
B. eft
C. lst
D. lft
Answer» C. lst
54.

……….is the latest time by which an activity can be finished without delaying the completion of the project.

A. est
B. eft
C. lst
D. lft
Answer» D. lft
55.

……………is the duration by which an activity can be delayed without delaying the project

A. slack
B. total float
C. free float
D. independent float
Answer» B. total float
56.

……… is the time by which the completion of an activity can be delayed beyond its earliest finish time without affecting the earliest start time of a succeeding activity

A. slack
B. total float
C. free float
D. independent float
Answer» C. free float
57.

……….is activity oriented.

A. cpm
B. pert
C. lp
D. none of the above
Answer» A. cpm
58.

………. is event oriented.

A. cpm
B. pert
C. lp
D. none of the above
Answer» B. pert
59.

PERT emphasis on ………..

A. time
B. activity
C. a) and b)
D. none of the above
Answer» A. time
60.

Full form of PERT is

A. performance evaluation review technique
B. programme evaluation review technique
C. programme evaluation research technique
D. none of these.
Answer» B. programme evaluation review technique
61.

…….. is a scheme or design of something intended or device.

A. programme
B. project
C. network
D. float
Answer» C. network
62.

An activity which must be completed before one or more other activities start is known as …………activity.

A. dummy
B. predecessor
C. successor
D. none of these
Answer» B. predecessor
63.

The event is commonly represented by …… in network diagram

A. nodes
B. arrow
C. triangle
D. none of these
Answer» A. nodes
64.

…….is the disconnection of an activity before the completion of activities in a project network diagram.

A. dangling
B. looping
C. dummy
D. none of the above
Answer» C. dummy
65.

…………..is an activity oriented diagram.

A. cpm
B. pert
C. histogram
D. none of the above
Answer» A. cpm
66.

………… is the duration by which an activity can be delayed without delaying the project.

A. total float
B. slack
C. earliest event time
D. none of these
Answer» A. total float
67.

………is the shortest possible time in which an activity can be delayed without delaying the project.

A. pessimistic time estimate
B. optimistic time estimate
C. most likely time estimate
D. none of these
Answer» B. optimistic time estimate
68.

Which of the following is not a part of decision tree problem specification?

A. a list of alternatives
B. a list of possible state of nature
C. evpi
D. pay off associated with alternative/ state of nature combination.
Answer» C. evpi
69.

If a decision theory problem has 3 decision alternatives and 4 states of nature, the number of payoffs in that problem will be

A. 3
B. 4
C. 12
D. 64
Answer» C. 12
70.

In a decision theory problem under complete uncertainty, which one of the following approaches will not be possible?

A. expected monetary value
B. maxmin
C. minimax
D. hurwicz
Answer» A. expected monetary value
71.

For decision making under uncertainty, identify the decision rule that is appropriate for the optimist.

A. laplace
B. maximax
C. minimax regret
D. maxmin
Answer» B. maximax
72.

What decision-making condition must exist for the decision tree to be a valuable tool?

A. certainty
B. uncertainty
C. risk
D. it does not matter, the tool is appropriate in all environments
Answer» C. risk
73.

Which of the following is (are) types of decision-making environments?

A. decision making under uncertainty
B. decision making under certainty
C. decision making under risk
D. none of the above
Answer» B. decision making under certainty
74.

A good decision always implies that

A. will obtain the best final results
B. have used appropriate quantitative analysis.
C. have considered all alternatives
D. have followed a logical process.
Answer» D. have followed a logical process.
75.

All of the following are steps in the decision-making process EXCEPT

A. define the problem
B. list alternatives
C. identify the possible outcomes
D. compute the posterior probabilities.
Answer» D. compute the posterior probabilities.
76.

The equally likely decision criteria is also known as

A. bayes
B. laplace
C. minimax
D. hurwicz
Answer» B. laplace
77.

Opportunity loss refers to

A. the expected value of a bad decision
B. the expected loss from a bad decision
C. the difference between actual pay off and the optimal pay off
D. the regret from not having made a decision
Answer» C. the difference between actual pay off and the optimal pay off
78.

The criteria of expected monetary value is used for making decisions under

A. certainty
B. uncertainty
C. risk
D. all of the above
Answer» D. all of the above
79.

The maximax criteria is……..

A. optimistic
B. neutral
C. pessimistic
D. can be any one of the above
Answer» C. pessimistic
80.

Which of the following might be viewed as an optimistic decision criterion?

A. hurwicz criterion
B. maximin
C. maximax
D. minimax
Answer» C. maximax
81.

The minimum EOL will always result in the same decision as

A. minimax
B. maximin
C. maximum emv
D. maximax
Answer» C. maximum emv
82.

Decision theory is concerned with

A. methods of arriving at an optimal decision
B. selecting optimal decision in sequential manner
C. analysis of information that is available
D. all of the above
Answer» D. all of the above
83.

Which of the following criterion is not used for decision making under uncertainty?

A. maximin
B. maximax
C. minimax
D. minimize expected loss
Answer» D. minimize expected loss
84.

The minimum expected opportunity loss is

A. equal to evpi
B. minimum regret
C. equal to emv
D. both (a) and (b)
Answer» D. both (a) and (b)
85.

The expected value of perfect information is equal to

A. eppi – minimum emv
B. eppi + maximum emv
C. maximum eol
D. none of the above
Answer» A. eppi – minimum emv
86.

The value of the coefficient of optimism is needed while using the criterion of

A. equally likely
B. maximin
C. realism
D. maximin
Answer» C. realism
87.

while using Hurwicz criterion, the coefficient of realism

A. represents the degree of optimism
B. represents the degree of pessimism
C. is the probability of state of nature
D. none of the above
Answer» A. represents the degree of optimism
88.

The decision making criteria that should be used to achieve maximum long term pay off is

A. eol
B. emv
C. hurwicz
D. maximax
Answer» B. emv
89.

Game theory models are classified by the

A. number of players
B. sum of all payoff
C. number of strategies
D. all of the above
Answer» D. all of the above
90.

The objective of network analysis is to

A. minimize total project duration
B. minimize total project cost
C. minimize production delays, interruption and conflicts
D. all of the above
Answer» A. minimize total project duration
91.

The initial solution of a transportation problem can be obtained by applying any known method. But the only condition is

A. the solution be optimal
B. the rim conditions are satisfied
C. the solution not be degenerate
D. all of the above
Answer» B. the rim conditions are satisfied
92.

When total supply is equal to total demand in a transportation problem , the problem is said to be

A. balanced
B. unbalanced
C. degenerate
D. none of the above
Answer» A. balanced
93.

The term “Operation Research” was coined by :

A. Mc Closky and Trefthen
B. Arthur Clark
C. Churchman, Ackoff and Arnoff
D. George B Dantzig
Answer» A. Mc Closky and Trefthen
94.

Management Science came into existence in a ................... context.

A. Business
B. Academic
C. Military
D. Religious
Answer» C. Military
95.

By the beginning of ........................., the industries in USA realised the importance of Management Science in solving business and management problems.

A. 1930s
B. 1940s
C. 1950s
D. 1960s
Answer» C. 1950s
96.

In India, Operations Research came into existence in the year ..............

A. 1940
B. 1947
C. 1949
D. 1950
Answer» C. 1949
97.

In India, first Operations Research unit was set up at .................................

A. Regional Research Laboratory, Hyderabad
B. Indian Statistical Institute, Kolkotha
C. Indian Institute of Science and Technology, Bengaluru
D. Indian Institute of Science and Technology, Mohali
Answer» A. Regional Research Laboratory, Hyderabad
98.

In India, first Operations Research application was made by ...........................

A. Pranab K Sen
B. Prof. Mahalonobis
C. Samarendra Nath Roy
D. Raghu Raj Bahadur
Answer» B. Prof. Mahalonobis
99.

Operations Research Society of India was formed in the year ..................

A. 1950
B. 1955
C. 1957
D. 1960
Answer» C. 1957
100.

Who defined Operations Research as “the art of giving bad answers to problems which otherwise have worse answers”?

A. H M Wagner
B. H A Taha
C. T L Saaty
D. Arthur Clark
Answer» C. T L Saaty

Done Studing? Take A Test.

Great job completing your study session! Now it's time to put your knowledge to the test. Challenge yourself, see how much you've learned, and identify areas for improvement. Don’t worry, this is all part of the journey to mastery. Ready for the next step? Take a quiz to solidify what you've just studied.