Q.

In the given figure, the network of a project represents

A. Activity of an excavation of a footing
B. Activity of an excavation which starts at event No. 1 and ends at even No.2
C. Activity of excavation which takes 8 units of time
D. None of these
Answer» C. Activity of excavation which takes 8 units of time