In the given figure, the network of a project represents |
A. | Activity of an excavation of a footing |
B. | Activity of an excavation which starts at event No. 1 and ends at even No.2 |
C. | Activity of excavation which takes 8 units of time |
D. | None of these |
Answer» C. Activity of excavation which takes 8 units of time |